Upcoming Operations
- Underpinning works.
- Site clearance for piling works and capping beam.
- Transportation of interior brickwork to storage.
- Piling operations.
- Excavation.
- Continuation of marketing suite fit out.
- Visit of students from Folkestone college.
Current on-Site Activities
- Continued dismantle.
- Groundworks.
- Preparation for piling works.
Contact Us