November 2022 Residents Newsletter
Dear Neighbours,
Welcome to issue #5 of our monthly residents newsletter that covers activities carried out in November. It has been a busy month for us pushing on with the piling so we can start the excavation.
Upcoming Operations
- Completion of piling operations.
- Excavations for capping beam.
- Start to pour capping beam.
- Mock up unit for terracotta stone.
- Fit temporary electrical supply.
Current on-Site Activities
- Piling operations in preparation for excavation.
- Fit out of the marketing suite.
- Preparation for temporary electrical supply.
- Temporary works to support the existing building.
- Fitting of bollards to protect Leas green area.
Contact Us
It is our intention to complete our works with minimal disruption to the local community. However, if you have any concerns, please contact the following:
Project Director:
Ahmet Ozdemir
aozdemir@antyapi.co.uk
07391 865189
Construction Manager:
Ali Atakan
aatakan@antyapi.co.uk
0779 6323332
Head of Health Safety:
Lawrence McKenzie
lmckenzie@antyapi.co.uk
07479 864071